Funding Agencies

NABARD RIDF Tranche XIX- Second phase - 2013-2014

  • No. of Projects - 51
  • Total Amount - 50.72 Crore
  • No. of Projects completed - 10
  • No of Ongoing Projects - 41

Sl No.

Name of the Project

AS amount

Physical status

Photographs

1

Construction of Anganvadi no 5 Chappanam

11

Work Completed


View Photo

2

Construction of Fishermen Utility Centre at Karumkulam

120

Work Completed


View Photo

3

Construction of New building for Anganvadi at Anchuthengu

11

Work Completed


View Photo

4

Construction of new building for Anganvadi at Thalikkulam

12.6

Work Completed


View Photo

5

Construction of new building for Anganvadi no 57, Puthiyakadappuram

17.5

Work Completed


View Photo

6

Construction of new building for Anganvadi no 90 Kumbalam

10

Work Completed


View Photo

7

Construction of new building for sub centre at Purakkad

42

Work Completed


View Photo

8

Drainage construction at Padinjare manakkodam

200

Work Completed


View Photo

9

Drainage construction at Vadakkekad Colony

144

Work Completed


View Photo

10

Ground improvement of technical high school payyoli , Iringal

17

Work Completed


View Photo

11

Construction of new building for SNM LP School, Kottuvallikkad

59.55

Work Nearing Completion


View Photo

12

Construction of Fishermen Utility Centre at Adimalathura

187

Work in Progress


View Photo

13

Construction of Fishermen Utility Centre at Nattika

187

Work in Progress


View Photo

14

Construction of New building for Anganvadi at Puthiyangadi

16

Work in Progress


View Photo

15

Construction of new building for Anganvadi no 95, Kumbala

18

Work in Progress


View Photo

16

Construction of New building for Anganvadi no95, Shiriya

18

Work in Progress


View Photo

17

Construction of new building for Ayurveda Hospital at Pallipuram

323

Work in Progress


View Photo

18

Construction of new building for Govt HS School, Chandragiri

140

Work in Progress


View Photo

19

Construction of new building for Govt LP School , Kadalundi Nagaram

85

Work in Progress


View Photo

20

Construction of new building for Govt LP School, Puthenkadappuram.

73

Work in Progress


View Photo

21

Construction of new building for Govt VHSS,Paravanna

209

Work in Progress


View Photo

22

Construction of new building for Govt. UP School, Purathoor

98

Work in Progress


View Photo

23

Construction of new building for Govt.Higher Secondary School, Mangalam

202

Work in Progress


View Photo

24

Construction of new building IP and OP block for PHC, Puthukurichy

230

Work in Progress


View Photo

25

Construction of new building IP block for PHC, Neendakara

190

Work in Progress


View Photo

26

Construction of new building IP Block for PHC, Thalikkulam

180

Work in Progress


View Photo

27

Construction of sub centre at Mangalam

28

Work in Progress


View Photo

28

Construction of sub centre at Nattika

29

Work in Progress


View Photo

29

Construction of sub centre at Vettoor

30

Work in Progress


View Photo

30

Drainage construction at Neendakara, Kuttanazhikam.

180

Work in Progress


View Photo

31

Water Supply scheme to Poyya

410

Work in Progress


View Photo

32

Construction of new IP block building for Pallithodu Hospital

168

Work Commenced


View Photo

33

Construction of new building for Anganvadi no 72 Purakkad

18.5

Work yet to Commence

 

34

Construction of new I P block building for Poothotta Hospital

145

Work yet to Commence


View Photo

35

Construction of new IP Block for Kattoor Chettikkad Hospital

171

Work yet to Commence

 

36

Drainage construction at Kairalimukku

19

Work yet to Commence

 

37

Construction of Fishermen Utility Centre at Ajanur

129

Tendered

 

38

Construction of Fishermen Utility Centre at Thalikkulam

126

Tendered

 

39

Construction of new building for Anganvadi no 73, Purakkad

18.5

Tendered

 

40

Construction of Sub centre at Puthiyathura

30

Tendered

 

41

Construction of Anganvadi at Puthenthura

15.1

Pre-project activities in progress

 

42

Construction of Anganvadi no 124 at Elakunnapuzha

11.25

Pre-project activities in progress

 

43

Construction of Anganvadi no 127 at Elakunnapuzha

11.25

Pre-project activities in progress

 

44

Construction of Dispensary at Adimalathura

17

Pre-project activities in progress

 

45

Construction of Fishermen Utility Centre at Puthiyangadi

178

Pre-project activities in progress

 

46

Construction of New building for Anganvadi No 114 at Ochamukku.

11.25

Pre-project activities in progress

 

47

Construction of new building for Balasadanam Anganvadi No 38

10.6

Pre-project activities in progress

 

48

Construction of new building for Govt HS School, Azhikkode

200.5

Pre-project activities in progress

 

49

Construction of new building for Govt LP School, Avil Beach

85

Pre-project activities in progress

 

50

Construction of new IP block for PHC, Payyoli

123

Pre-project activities in progress

 

51

Construction of new PHC at Kuriyadi

106.5

Pre-project activities in progress

 

Total

5072.1